The initial step of the infrastructural equipment of the park’s first stage will be completed by October 1, 2013.

06 Сентября 2013

The initial step of the infrastructural equipment (providing residents with gas fuel, electricity, water supply networks, sewer, fiber-optic communication lines, road network) of the park’s first stage will be completed by October 1, 2013.

In particular, the diversion unit and the water supply network was passed.

LLC «MonolitStroj Tula» (Russia) performs the first stage of road construction which consist of intra passages, storm sewer system and lighting.

LLC PCF «Electroshield» (Russia) started to prepare the foundation of transformer substations with the distribution point. The contractor branch of the JSC «IDGC of Center» — «Orelenergo» organized construction of two cable lines that will connect it to the substation in Mtsensk.

LLC MPC «Unistroy» (Russia) provides engineering preparation of the area for the creation of internal and external networks of gas supply, sewerage and communications.

Начальный этап оснащения первой очереди парка инфраструктурой

← All news
Земли промышленного назначения Industrial areas for production placement in the industrial park "Green grove"

Sale from 600000 rub/ha
Rent from 25000 rub/ha in year